CCWD Reach 3A Project Update: Week Of April 3rd
Arnold, CA...With the improved weather conditions, CCWD’s contractor (T&S Construction) has been able to resume work on the Reach 3A Pipeline Replacement Project. Construction generally begins at 7 a.m. and ends around 3:30 p.m. Here’s the proposed construction schedule for the next three weeks (this schedule is subject to change).
Construction update: April 3 – April 21
Monday April 3: Crews will install a gate valve near the Secured Self Storage on Fir Street.
Tuesday April 4: Crews will be digging pot holes, installing plates and cutting in a gate valve for Lilac Park. The work will take place at the intersection of Blagen Road, Dunbar Road and Highway 4 and will cause traffic delays.
Wednesday April 5: Crews will perform back-filling and potholing operations near Lilac Park. The work will take place at the intersection of Blagen Road, Dunbar Road and Highway 4 and will cause traffic delays.
Thursday April 6: Crews will be back filling the gate valve they installed serving Lilac Park. Once installed the gate valve will be covered with steel plates.
April 6, 7 and 10: Crews will be saw cutting on Oak Court down Fir Street, crossing Manuel Road and Sequoia Street and Oak Circle ending up at the West end of Blagen Road and Dunbar Road. These operations will cause traffic delays in the area of the saw cutting.
Tuesday April 11: Crews will cut in a gate valve to serve Lilac Park, which may create a temporary water outage for residents and businesses in the downtown Arnold area. Specifics on this planned outage will be posted separately. This work will cause significant traffic delays at the intersection of Blagen Road, Dunbar Road and Highway 4.
Wednesday April 12: Crews will cut in a gate valve near the cabinet shop at the far west end of Sequoia Street. This work will cause traffic delays.
Thursday April 13 & Friday April 14: Crews will excavate and set two pressure-reducing valves at the intersection of Manuel and Fir Streets. Residents living in Mill Woods will experience traffic delays.
Monday April 17 through Friday April 21: Crews will start trenching and installing a 12″ water transmission line between the west end of Sequoia Street moving east, crossing Manuel and Fir Streets and continuing down Fir Street. This work will cause traffic delays in the area.
As of April 2017, T&S Construction has replaced about 15,000 feet of pipeline and another 4,000 feet remain – the project is about 80 percent finished. The remaining portions of pipeline that need to be replaced are along Pine Drive, Oak Court, Oak Circle, Sequoia Street, Fir Street, Dunbar (from Fir to Highway 4) and from Chevron to Henry Street on Blagen Road. Substantial completion of the project will most likely be in July 2017.
Those with questions or concerns about the project, may call CCWD at (209) 754-3543 or email customerservice@ccwd.org.
|
Comments - Make a comment |
The comments are owned by the poster. We are not responsible for its content. We value free speech but remember this is a public forum and we hope that people would use common sense and decency. If you see an offensive comment please email us at news@thepinetree.net
|
What's Related |
These might interest you as well
Photo Albums
Local News
- The Arnold Summer Pancake Breakfasts Return for Memorial Day, July 4th...
- Richard "Dick" Haight 1931 ~ 2024
- Mornings with the One Percent™ Classic Rewind, The 2023 Arnold Car Show
- Big Trees Market Weekly Ad, Grocery, Produce, Meat & Deli Specials Thr...
- Traffic Update....Collison Near Sr4 / Howard Ct
- Traffic Update....Possible Injury Vehicle vs Porsche Collision Near Sr4...
- Chapel in the Pines Sunday Service, May 19, 2024
- Big Trees Market Weekly Ad, Grocery, Produce, Meat & Deli Specials Thr...
- The Arnold Summer Pancake Breakfasts Return for Memorial Day, July 4th...
- Lots of Firewise Community Members Packed Independence Hall
Link Manager
Web Pages
RSS News Feeds
Calendar
phpws Business Directory
|
|
|